A date must identify its event

A task can have planned, observed and recorded dates. They are not interchangeable. Exporting a model after a planned date does not prove the intervention occurred. Retain status, responsibility, observation source and time precision. When reconciling systems, preserve the applicable offset or timezone. Ten o’clock at UTC+02:00 is eight o’clock UTC; deleting the offset introduces a two-hour ambiguity and may misorder events from separate systems.

Calculate cost within a consistent scope

Cost links quantity, unit, unit price, currency, date and scope. Twenty verified square metres at thirty-five euros per square metre give seven hundred euros for that item. Taxes, other works, indexation and fees are not automatically included. Check the area definition: a geometric quantity is not necessarily the contract’s measurable or billable quantity. Retain assumptions and price source before comparing scenarios or presenting precision unsupported by the inputs.

Retain measurements with context

A performance value needs quantity, unit, timestamp, conditions and source. One observation is not a trend, and a stale series does not establish live monitoring. Separate measured value, setpoint and trigger threshold. Maintenance may be triggered by duration, condition or performance, under a defined policy. Do not automatically create a task from a number whose meaning is unknown, and record uncertainty rather than silently assigning it an operational status.

Make events explainable

For correction or replacement, retain previous state, event, evidence, date and authorised actor. A new asset should not silently inherit every intervention on its predecessor. Functional position may stay stable while the physical instance changes; document the distinction and identity policy. The target must allow history to be read after import and update. A complete register without an update owner quickly deteriorates, even when its first delivery passed every information check.

Worked example

Fictional case: replacement covers 20 m² at €35/m², giving €700 for that item only. A check measurement is timestamped 10:00 UTC+02:00, or 08:00 UTC. Mapping retains quantity, unit, price, instant and source; no real construction history is claimed.

  1. Measurement / quantity
  2. Unit + time + source
  3. Decision / task / cost
  4. Event + updated history

Questions and answers

A task has a planned start date. Can it be reported as its observed actual start?

No; retain planned status and seek evidence of actual start. Planned, actual and recorded dates differ. A 4D link does not replace execution or acceptance evidence.

A measurement is timestamped 10:00 at UTC+02:00. Which UTC time is the same instant?

08:00 UTC Subtract the explicit two-hour offset. Keep source timestamp, timezone, quantity and unit; missing time context can misalign a time series.

Put it into practice

Review cards and solve cases

Start free training →Worked example IFC →

Official sources

Content references: 30 October 2026. Consult the sources to verify their version and applicability.

Published by BIMCheck Consulting · Publisher: Winter Fernandes

Content references: 30 October 2026. Consult the sources to verify their version and applicability.

Independent, non-certifying training. Check the IFC schema, standards edition and project-specific requirements.

About and editorial method